| 000 | 01560cab a2200217 4500 | ||
|---|---|---|---|
| 001 | ABS39828 | ||
| 008 | 090401t1988 xxu||||| |||| 00| 0 eng d | ||
| 035 | _a(Sirsi) u19209 | ||
| 041 | _aeng | ||
| 245 | _aShanning International Ltd v George Wimpey International Ltd | ||
| 260 | _c1988 | ||
| 300 | _aj | ||
| 350 | _a0 | ||
| 490 |
_aNew Law Journal _v(1988) 279-280(2) |
||
| 520 | _aCA 8 September 1988. Appeal by main contractor (G) from official referee`s (R) decision, ordering G to make an interim payment of £350,000 to the subcontractor (S) under RSC Order 29 rule 12(c). A dispute arose between the two parties involved in construction of a hospital in Oman , and S issued a writ claiming £969,000 from G, in respect of goods and retention money s. S applied for summary judgment under Order 14, or alternatively, interim payment under Order 29. G admitted that it owed £904.000 to S, but claimed that this amount was subject to a set-off and counterclaim which would extinguish the admitted claim. R refused to enter judgment under Order 14, but ordered G to make an interim payment of £350,000. G appealed, contending that R could not have been satisfied that if the action proceeded to trial S would obtain judgment for a substantial sum, and therefore he should not have made the interim payment order. In R`s view, the correct approach was for the court to ask itself: | ||
| 650 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||
| 650 | _aCLAIMS | ||
| 690 | _aBUILDING AND CONSTRUCTION-CASE LAW | ||
| 942 | _n0 | ||
| 948 | _c04/03/1997 | ||
| 999 |
_c12799 _d12799 |
||