245 0 0 _aMeasure for measurements
260 _c1996
350 _a0
490 0 _aBuilding
_v261(7963) 25 October 1996, 32-33(2)
520 _aConsiders a dispute involving SMM6 and the difference between provisional sums and prime cost sums: "St Modwen Developments v Bowmer and Kirkland" (ORC, X84986).
650 2 4 _aJCT STANDARD FORM OF BUILDING CONTRACT (1980 EDITION)
650 2 4 _aSTANDARD METHOD OF MEASUREMENT (SIXTH EDITION)
650 2 4 _aST MODWEN DEVELOPMENTS V BOWMER AND KIRKLAND
651 4 _aEngland and Wales