| 245 | _aEngineer`s decision is vital | ||
| 260 | _c1988 | ||
| 350 | _a0 | ||
| 490 |
_aContract Journal _v346(5691) 10 November 1988, 9(1) |
||
| 520 | _aDiscusses the recent case Anglian Water Authority v RDL Contracting Ltd , (1988), which concerned the concept under ICE Conditions of contract clause 66(1) that the engineer can give a `decision` on disputes arising under the contract. | ||