245 _aEngineer`s decision is vital
260 _c1988
350 _a0
490 _aContract Journal
_v346(5691) 10 November 1988, 9(1)
520 _aDiscusses the recent case Anglian Water Authority v RDL Contracting Ltd , (1988), which concerned the concept under ICE Conditions of contract clause 66(1) that the engineer can give a `decision` on disputes arising under the contract.