| 245 | _aGateshead MBC v SoS Environment and Northumbrian Water Group plc | ||
| 260 | _c1994 | ||
| 350 | _a0 | ||
| 490 |
_aProperty and Compensation Reports _v(1994) 67 P&CR 179-191(13) |
||
| 520 | _aQBD 29 September 1993. The grant of outline planning permission for a clinical waste incinerator on appeal from N, contrary to the Inspector`s recommendations, was challenged in the courts by G. G argued that SoS`s reliance on the EPA pollution controls alone was not a lawful route for a planning decision; that the controls themselves were not shown to be sufficient in the circumstances; and the SoS had not justified his departure from the Inspector`s opinion. The court dismissed G`s application considering there to be legitimate overlap between planning and pollution control and that the SoS had presented his reasons intelligibly. | ||
| 650 | _aENVIRONMENTAL PROTECTION ACT 1990 | ||
| 650 | _aMATERIAL CONSIDERATIONS | ||
| 650 | _aPLANNING CONTROL | ||
| 650 | _aPOLLUTION CONTROL | ||
| 650 | _aSTRUCTURE PLAN | ||
| 650 | _aTOWN AND COUNTRY PLANNING ACT 1990 S288 | ||
| 650 | _aWASTE INCINERATORS | ||
| 690 | _aPLANNING LAW AND PRACTICE-CASE LAW | ||