000 01569cab a2200217 4500
001 X2741
008 090401t1990 xxu||||| |||| 00| 0 eng d
035 _a(Sirsi) u26026
041 _aeng
245 _aMJ Gleeson plc v Taylor Woodrow Constructions Ltd
260 _c1990
350 _a0
490 _aConstruction Industry Law Letter
_v1990 CILL 578(1)
520 _aQBD 10 December 1989. T, management contractors to the DoE, sub-let a Works Package to G. G were entitled to monthly advance payments and the subcontract provided that "when the valuation has been agreed by the SoS, the MC shall certify the same to be paid by way of advance". G claimed an extension of time of 73.5 days, T granted 39. In October 1987 T wrote to G to recover money due because of their failure to complete on time and included a list of set off claims and calculation of liquidated damages leaving G with £496,781. Later T issued a Subcontract Payment Authority No 12 deducting £95,360 for set off and £36,000 for liquidated damages. G agreed that the liquidated damage sum and their extension of time were independent and therefore the subject of arbitration However they claimed the set off payments had been improperly deducted. Despite repeated requests by G for particulars of the set-off claims T had failed to supply them. T claimed they were due to delay and this meant the
650 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
650 _aCASE LAW
650 _aCLAIMS
690 _aBUILDING AND CONSTRUCTION-CASE LAW
942 _n0
948 _c04/03/1997
999 _c17467
_d17467