| 000 | 01568cab a2200205 4500 | ||
|---|---|---|---|
| 001 | ABS41222 | ||
| 008 | 090401t1989 xxu||||| |||| 00| 0 eng d | ||
| 035 | _a(Sirsi) u28933 | ||
| 041 | _aeng | ||
| 245 | _aArchitectural Installation Services Ltd v James Gibbons Windows Ltd | ||
| 260 | _c1989 | ||
| 350 | _a0 | ||
| 490 |
_aConstruction Industry Law Letter _v(1989) CILL 512-513(2) |
||
| 520 | _aORC 14 June 1989 A contracted in July 1985 to supply specialist labour only to J, as main contractor s, for installing window units and ancillary services. A sued for money alleged to be due and for damages for wrongful determination of the contract. J said they were entitled to determine the contract and counterclaimed for, among other things, damages for defective work. Two preliminary issues were to be tried. Each assumed that A had wholly suspended the works and/or failed to proceed with the works expediously, in breach of cl 20 of the contract. The first issue was: on these assumptions, was J`s telex of 21 August 1986 a rightful termination of the subcontract pursuant to cl 8; the second issue, again on the same assumptions, but such as to evince an intention on the part of A no longer to be bound by the subcontract, was whether J`s telex was a rightful determination at common law. In each case the alternative to rightful determination was unlawful repudiation. ORC held that J`s | ||
| 650 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||
| 650 | _aCLAIMS | ||
| 690 | _aBUILDING AND CONSTRUCTION-CASE LAW | ||
| 942 | _n0 | ||
| 948 | _c04/03/1997 | ||
| 999 |
_c19466 _d19466 |
||