| 245 | _aFKI Engineering plc v Metro-Cammell Hong Kong Ltd | ||
| 260 | _c1996 | ||
| 350 | _a0 | ||
| 490 |
_aConstruction Industry Law Letter _v[1996] CILL 1162-1163(2) |
||
| 520 | _a29 January 1996. Costs- duty of an arbitrator to act judicially - power of courts to review arbitral costs awards - winner takes all. (HEADNOTE FROM JOURNAL). | ||
| 650 | _aARBITRATORS | ||
| 650 | _aCOSTS AWARDS | ||
| 650 | _aFKI ENGINEERING PLC V METRO-CAMMELL HONG KONG LTD | ||
| 650 | _aREPAIR WORK | ||