520 _aWith reference to the case Mitsui Construction Co Ltd v Attorney-General of Hong Kong, which concerned whether increases in quantities entitled contractors to new rates and prices, this article discusses the difficulties involved in the interpretation of standard forms of contract.
650 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
650 _aFIDIC
650 _aICE CONDITIONS OF CONTRACT
690 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS