| 100 | _aPowell-Smith, V. | ||
| 245 | _aDon`t be misled by comparisons | ||
| 260 | _c1987 | ||
| 350 | _a0 | ||
| 490 |
_aContract Journal _v22 January 1987, 9 (1) |
||
| 520 | _aWith reference to the case Mitsui Construction Co Ltd v Attorney-General of Hong Kong, which concerned whether increases in quantities entitled contractors to new rates and prices, this article discusses the difficulties involved in the interpretation of standard forms of contract. | ||
| 650 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||
| 650 | _aFIDIC | ||
| 650 | _aICE CONDITIONS OF CONTRACT | ||
| 690 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||