| 245 | _aQuantifying disruption costs | ||
| 350 | _a0 | ||
| 490 |
_aConstruction Law Journal _v5(4) 258-262(5) |
||
| 520 | _aDescribes the process of quantifying disruption costs according to points made in Crosby Ltd v Portland UDC (1967), namely additional costs to individual disrupting events are not allocated and the contractor must give information for checking by the recipient of claims . | ||