| 000 | 01482cab a2200181 4500 | ||
|---|---|---|---|
| 001 | ABS41953 | ||
| 008 | 090401t1989 xxu||||| |||| 00| 0 eng d | ||
| 035 | _a(Sirsi) u33673 | ||
| 041 | _aeng | ||
| 245 | _aAcsim (Southern) Ltd v Danish Contracting and Development Co Ltd | ||
| 260 | _c1989 | ||
| 350 | _a0 | ||
| 490 |
_aConstruction Industry Law Letter _v1989 CILL 538-540(3) |
||
| 520 | _aCA 27 October 1989. Discussion of the case. Acsim (A) were engaged by Dancon (D) under a subcontract incorporating with amendments the Blue Form . D were owners of the building and the main contractor . There was no main contract. A made an interim application for payment, claiming 98% completion. D refused to pay and asserted claims greatly in excess of A`s application and alleged damage and delay by them. A sought judgement on its interim application. At the hearing, D relied upon the affidavit of their project manager as to cross claims. The affidavit also indicated that there was further evidence that might show that A`s application was not justified by the work carried out. D sought an adjournment to obtain further expert advice. This was refused on the grounds that it would be legally irrelevant; under the Blue Form the main contractor`s only right of set off was in cl.15. D had failed to comply with cl.15., therefore the judge gave A summary judgement. D appealed and sought to | ||
| 690 | _aBUILDING AND CONSTRUCTION-CASE LAW | ||
| 942 | _n0 | ||
| 948 | _c04/03/1997 | ||
| 999 |
_c22454 _d22454 |
||