000 01482cab a2200181 4500
001 ABS41953
008 090401t1989 xxu||||| |||| 00| 0 eng d
035 _a(Sirsi) u33673
041 _aeng
245 _aAcsim (Southern) Ltd v Danish Contracting and Development Co Ltd
260 _c1989
350 _a0
490 _aConstruction Industry Law Letter
_v1989 CILL 538-540(3)
520 _aCA 27 October 1989. Discussion of the case. Acsim (A) were engaged by Dancon (D) under a subcontract incorporating with amendments the Blue Form . D were owners of the building and the main contractor . There was no main contract. A made an interim application for payment, claiming 98% completion. D refused to pay and asserted claims greatly in excess of A`s application and alleged damage and delay by them. A sought judgement on its interim application. At the hearing, D relied upon the affidavit of their project manager as to cross claims. The affidavit also indicated that there was further evidence that might show that A`s application was not justified by the work carried out. D sought an adjournment to obtain further expert advice. This was refused on the grounds that it would be legally irrelevant; under the Blue Form the main contractor`s only right of set off was in cl.15. D had failed to comply with cl.15., therefore the judge gave A summary judgement. D appealed and sought to
690 _aBUILDING AND CONSTRUCTION-CASE LAW
942 _n0
948 _c04/03/1997
999 _c22454
_d22454