000 01139cab a2200205 4500
001 ABS42126
008 090401t1989 xxu||||| |||| 00| 0 eng d
035 _a(Sirsi) u34849
041 _aeng
245 _aCrown House Engineering Ltd v AMEC Projects
260 _c1989
350 _a0
490 _aConstruction Industry Law Letter
_v(1989) CILL 536-537(2)
520 _aCA 30 November 1989. Crown (C) carried out M & E works for AMEC (A); interim certificates were issued, but there was doubt as to whether a contract was ever concluded between C and A. C began proceedings against A for payment, pleaded initially in contract but later amended for a reasonable sum as quantum meruit . C started a second action against A for retention monies . In the main action C applied for an 0.29 interim payment; in the retention action C sought 0.14 summary judgement. They were successful in both applications. A appealed against both orders. Both of A`s appeals allowed.
650 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
650 _aCLAIMS
690 _aBUILDING AND CONSTRUCTION-CASE LAW
942 _n0
948 _c04/03/1997
999 _c22979
_d22979