245 _aJohn Mowlem & Co plc v Carlton Gate Development Co Ltd
260 _c1990
350 _a0
490 _aConstruction Industry Law Letter
_v(1990) CILL 584-585(2)
520 _aORC 15 May 1990. J applied for a 0.14 summary judgement (0.29 interim payment for unpaid architect`s interim certificate . The C applied for a stay of proceedings under the Arbitration Act 1950 s4 . Matters raised were what was suitable for Order 14 hearing, inappropriate cases to be discouraged where there is an arbitration clause. It was held that the summary shall be dismissed and referred to an arbitrator.
650 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
650 _aCLAIMS
690 _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ARBITRATION