000 01468cab a2200193 4500
001 ABS43032
008 090401t1990 xxu||||| |||| 00| 0 eng d
035 _a(Sirsi) u40075
041 _aeng
245 _aRosehaugh Stanhope v Redpath Dorman Long
260 _c1990
350 _a0
490 _aConstruction Industry Law Letter
_v(1990) CILL 5096-598(3)
520 _aCA 26 June 1990. Appeal by RDL against a HC decision for damages for loss and expense against trade contractors . RS entered into contracts with various trade contractors including RDL. RS appointed Bovis/Schal Joint Venture as construction manager . RS sought damages in the HC on the basis that RDL had not completed by contractual completion date. The contract manager had made a bone fide estimate for loss and damage. RS argued that construction manager should have extended the completion dates beyond dates of actual completion and that completion date had been settled, they could not be bound for damages for failure to complete on time. They also claimed that they were entitled to set off their claim in separate proceedings. It was held that there was not evidence in the contract between parties of a breach of contract and that the Management contractor had not power to decide whether RDL had breached their contract. Appeal allowed.
650 _aBEAUFORT HOUSE DEVELOPMENT LTD V ZIMMCOR
690 _aBUILDING AND CONSTRUCTION-CASE LAW
942 _n0
948 _c04/03/1997
999 _c25669
_d25669