245 _aCementation Piling and Foundations Ltd v Aegon Insurance Company Ltd and another
260 _c1994
350 _a0
490 _aConstruction Law Journal
_v(1994) 10 CLJ 301-311(11)
520 _aHC 12 November 1992. In 1983 C was engaged as subcontractor to Sir Alfred McAlpine and Son Ltd to carry out certain piling works and to construct diaphragm walls at the submarine base at Barrow-in-Furness. The diaphragm walls were constructed by excavating cavaties in the sand. By 1985 it was discovered there were gaps in the walls allowing sand to escape and thus required rectification. It was admitted that the cause was due to design, materials or workmanship. A dispute arose as to whether costs of repair fell under the policy issued by the second defendant, Commercial Union, or that of the first, A. Held that the CU were liable to pay the costs.
650 _aCEMENTATION PILING & FOUNDATIONS LTD V AEGON INSURANCE
650 _aDIAPHRAGM WALLS
650 _aPILING
650 _aSIR ALFRED MCALPINE AND SONS LTD
650 _aSUBMARINE BASES
690 _aBUILDING AND CONSTRUCTION-CASE LAW