000 01482cab a2200193 4500
001 ABS43436
008 090401t1990 xxu||||| |||| 00| 0 eng d
035 _a(Sirsi) u41711
041 _aeng
245 _aBlexen Ltd v G Percy Trentham Ltd
260 _c1990
350 _a0
490 _aEstates Gazette
_v(1990) 42 EG 133-137(3)
520 _aCA 23 May 1990. B were subcontractors appointed by the main contractor (G). The subcontract works were carried out between July and November 1984. Disputes as to the amount due from the main contractors to the subcontractors were referred to arbitration. B claimed the amount owing was £221,000, however G said the total sum under the contract was £285,000, £278,000 of which had been paid leaving £7,000. On 4 August 1986 G made a sealed offer to settle claims in the arbitration for the sum of £77,000 including interest to date. The offer was not accepted. On 3 February 1987 the arbitrator made an interim award in which he offered B £52,958 including interest to date of the award. The equivalent with interest to 4 August only, ie the date of the sealed offer, was £49,867, £27,000 less than the offer. The question then arose as to who should claim costs . B claimed them saying that they were the successful party in the arbitration having recovered an award of nearly £53,000. G claimed th
650 _aBLEXEN LTD V G PERCY TRENTHAM LTD
690 _aARBITRATION-CASE LAW
942 _n0
948 _c04/03/1997
999 _c26774
_d26774