| 100 | _aPowell-Smith, V. | ||
| 245 | _aGetting paid and lump sum contracts | ||
| 260 | _c1990 | ||
| 350 | _a0 | ||
| 490 |
_aContract Journal _v356 (5795) 8 November 1990, 6 (1) |
||
| 520 | _aThe author considers the reasons for withholding payment for lump sum contracts when work fails to get completed. | ||
| 650 | _aBUSINESS CONTRACTS | ||
| 650 | _aCLAIMS | ||
| 650 | _aDEFECTIVE WORK | ||
| 650 | _aHOLLAND HANNEN CUBITTS V WELSH HEALTH TSO | ||
| 650 | _aNON-PAYMENT RULE | ||
| 650 | _aSUMPTER V HEDGES | ||
| 690 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||