000 01596cab a2200229 4500
001 ABS43924
008 090401t1990 xxu||||| |||| 00| 0 eng d
035 _a(Sirsi) u44305
041 _aeng
245 _aJarvis Brent Ltd v Rowlinson Construction Ltd
260 _c1990
350 _a0
490 _aConstruction Industry Law Letter
_v(1990) CILL 620-622(3)
520 _aORC 13 December 1990 The contractor Jarvis Brent (JB) entered into a written agreement in JCT 1980 form with Rowlinson (R) to erect buildings in London. The completion date set by the contract and an extended date set by the architect passed without the works being completed. R sent JB a copy of a letter written to it by the quantity surveyor showing liquidated damages to date and the reduced amount of the interim certificate then due. This process was not repeated in relation to future interim certificates . Cheques were merely sent for lesser amounts than those certified. JB argued that on true construction of Clause 24.1 a written requirement was a condition precedent to recovery by R of liquidated damages and that neither the sending of the qs`s letter to JB nor the transmission of cheques in reduced amount constituted requirements in writing. R contended that JB was estopped from relying on this argument on the grounds that JB did not complain that the deductions were in breach
650 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
650 _aCASE LAW
650 _aCLAIMS
650 _aDEDUCTION
690 _aBUILDING AND CONSTRUCTION-CASE LAW
942 _n0
948 _c04/03/1997
999 _c28226
_d28226