000 01368cab a2200241 4500
001 ABS53519
008 090401t1995 xxu||||| |||| 00| 0 eng d
035 _a(Sirsi) u4882
041 _aeng
245 _aJames Lazenby & Co v McNicholas Construction Co Ltd
260 _c1995
350 _a0
490 _aAll England Law Reports
_v(1995) 3 AllER 821-841 (10)
520 _aQBD 7 November, 21 December 1994. In 1988, the plaintiff (L) began proceedings against M over the pricing and costs of a labour-only sub-contract. The proceedings were stayed pursuant to an arbitration clause in the contract. After 15 months L commenced arbitration. There was then a delay of 9 months and, in July 1992, M applied to strike out L`s claim under the Arbitration Act 1950 s13A . The application was rejected on the grounds that s13A came into force in January 1992 and was not retrospective. Following a HL decision in 1993 that s13A was retrospective, the arbitrator issued a final award in which he dismissed L`s claim under s13A. L appealed. Appeal allowed.
650 _aARBITRATION ACT 1950 S13A
650 _aCOURTS AND LEGAL SERVICES ACT 1990
650 _aDISMISSAL OF CLAIM
650 _aINORDINATE AND INEXCUSABLE DELAY
650 _aJAMES LAZENBY & CO V MCNICHOLAS CONSTRUCTION LTD
690 _aARBITRATION-CASE LAW
942 _n0
948 _c04/03/1997
999 _c2951
_d2951