| 100 | _aPowell-Smith, V. | ||
| 245 | _aAppealing judgment | ||
| 260 | _c1995 | ||
| 350 | _a0 | ||
| 490 |
_aContract Journal _v380(6041) 7 September 1995, 16(1) |
||
| 520 | _aDiscusses "Dew v North West Water", CA 1995, in which it was held that the main contractor (Dew) should be reimbursed for extra costs incurred as a result of employer variation. | ||
| 650 | _aADDITIONAL COSTS | ||
| 650 | _aCIVIL ENGINEERING CONTRACTS | ||
| 650 | _aDEW V NORTH WEST WATER | ||
| 650 | _aEMPLOYERS VARIATION | ||
| 650 | _aICE CONDITIONS OF CONTRACT | ||
| 650 | _aLOSS OF PROFIT | ||
| 650 | _aVARIATIONS | ||