000 01572cab a2200217 4500
001 ABS44626
008 090401t1991 xxu||||| |||| 00| 0 eng d
035 _a(Sirsi) u48084
041 _aeng
245 _aMcLaughlin and Harvey plc v P&O Developments Ltd
260 _c1991
350 _a0
490 _aConstruction Industry Law Letter
_v1991 CILL 677-678(2)
520 _aCommercial Court 18 April 1991. The contractors M entered into a agreement with P to construct an office block under JCT 1980 incorporating 1984/1986 amendments. Various disputes arose. In July 1990 the architect sent a final account to M who accepted it and in November 1990 they received a final certificate certifying the adjusted contract sum as that shown on the final account which M declined to accept. M wrote to the architect asking for an interim certificate and a discussion on the point. M received no answer so in December gave notice to concur the appointment of a arbitrator however the contract held that this should be issued within 14 days of the final certificate and it was then 15. M sought an extension of time from P for commencement of arbitration. P however argued that a valid arbitration had been launched by the December letter although not accepted by the architects. It was held that the delay was only one day and that discretion should be exercised in favour of M, t
650 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
650 _aCLAIMS
650 _aLAW CASE
690 _aBUILDING AND CONSTRUCTION-CASE LAW
942 _n0
948 _c04/03/1997
999 _c30215
_d30215