245 _aDeduction for completion delay
260 _c1993
350 _a0
490 _aIndependent
_v11 June 1993, 35(1)
520 _aIn "JF Finnegan ltd v Community Housing Association Ltd", ORC 4 June 1993, it was held that under JCT 1980 cl 24.2.1, which deals with liquidated and ascertained damages for delayed completion, the employer must make a requirement in writing of the contractor before making a deduction for liquidated damages.
650 _aCONTRACT CLAIMS
650 _aDELAYS
650 _aJCT STANDARD FORM OF BUILDING CONTRACT (1980 EDITION)
650 _aLIQUIDATED DAMAGES
690 _aBUILDING AND CONSTRUCTION-CASE LAW