| 245 | _aDeduction for completion delay | ||
| 260 | _c1993 | ||
| 350 | _a0 | ||
| 490 |
_aIndependent _v11 June 1993, 35(1) |
||
| 520 | _aIn "JF Finnegan ltd v Community Housing Association Ltd", ORC 4 June 1993, it was held that under JCT 1980 cl 24.2.1, which deals with liquidated and ascertained damages for delayed completion, the employer must make a requirement in writing of the contractor before making a deduction for liquidated damages. | ||
| 650 | _aCONTRACT CLAIMS | ||
| 650 | _aDELAYS | ||
| 650 | _aJCT STANDARD FORM OF BUILDING CONTRACT (1980 EDITION) | ||
| 650 | _aLIQUIDATED DAMAGES | ||
| 690 | _aBUILDING AND CONSTRUCTION-CASE LAW | ||