| 100 | _aPowell-Smith, V. | ||
| 245 | _aDispute stops interim claim | ||
| 260 | _c1991 | ||
| 350 | _a0 | ||
| 490 |
_aContract Journal _v361 (5849) 28 November 1991, 8(1) |
||
| 520 | _aDiscusses "Enco Civil Engineering Ltd v Zeus International Development Ltd" 29 October 1991 (unreported) which highlights the fact that interim certificates have no binding effect if contractual disputes arise. | ||
| 650 | _aCIVIL ENGINEERING CONTRACTS | ||
| 650 | _aCLAIMS | ||
| 650 | _aCONTRACTUAL OBLIGATIONS | ||
| 650 | _aICE CONDITIONS OF CONTRACT (FIFTH EDITION) | ||
| 650 | _aINTERIM CERTIFICATES | ||
| 690 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||
| 942 | _n0 | ||