| 000 | 01066cab a2200241 4500 | ||
|---|---|---|---|
| 001 | ABS45630 | ||
| 008 | 090401t1991 xxu||||| |||| 00| 0 eng d | ||
| 035 | _a(Sirsi) u54096 | ||
| 041 | _aeng | ||
| 245 | _aDeane v Bromley BC | ||
| 260 | _c1991 | ||
| 350 | _a0 | ||
| 490 |
_aRating & Valuation Reporter _v(1991) RVR 225-227(3) |
||
| 520 | _aLT 4 November 1991. Consent was given to reduce the height of 26 trees provided that the work be carried out by an approved contractor. The claimant maintained that he could have carried out the work himself at no cost. He was awarded the cost of the contractor`s fee with the estimated cost of hiring plant, which would have been required, deducted. | ||
| 650 | _aCOMPENSATION | ||
| 650 | _aPLANNING CONDITIONS | ||
| 650 | _aTOWN AND COUNTRY PLANNING ACT 1990 S205 | ||
| 650 | _aTREE PRESERVATION ORDERS (TPOs) | ||
| 690 | _aENVIRONMENTAL AND LAND CONSULTANCY-PLANNING AND DEVELOPMENT-COMPULSORY PURCHASE AND COMPENSATION | ||
| 690 | _aPLANNING LAW AND PRACTICE-CASE LAW | ||
| 942 | _n0 | ||
| 948 | _c04/03/1997 | ||
| 999 |
_c33174 _d33174 |
||