520 _aConsiders the ambiguity of the phrase `extension of time for completion` which can mean either `postponement of the date or the point in time by which completion of the contract work is to be expected` or `increase in the number of hours, days or weeks which are required to carry out the work in question`.
650 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
650 _aCLAIMS
650 _aCONTRACT CLAIMS
650 _aEXTENSION OF TIME