245 _aConstruction management contract
260 _c1992
350 _a0
490 _aNew Builder
_v(135) 25 June 1992, 13(1)
520 _aA case, which would define the responsibilities of the client and the contractor under construction management procurement, awaits further clarification of evidence before it can be heard in the High Court. The developers claim the contractors were responsible for the subcontractor`s work.
650 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
650 _aCONSTRUCTION MANAGEMENT
_96230
650 _aFARLANE PROPERTIES
650 _aJACOBS ISLAND
650 _aLEHRER MCGOVERN
650 _aSUBCONTRACTORS
650 _aTRAFALGAR HOUSE