| 245 | 3 | _aAn estimate is not always an estimate | |
| 260 | _c1992 | ||
| 350 | _a0 | ||
| 490 |
_aBuilding _v257(7747) 29 May 1992, 32(1) |
||
| 520 | _aWarns against inaccurate use of the work `estimate`, which it defines and discusses in relation to JCT contracts and case law. In "Crowshaw v Pritchard" for example, it was taken to mean `an offer`, a precedent which could lead to complications in practice. | ||
| 650 | _aDEFINITION | ||
| 650 | _aESTIMATE | ||
| 650 | _aESTIMATES | ||
| 690 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||