100 _aChevin, D.
245 _aChannel changer
260 _c1992
350 _a0
490 _aBuilding
_v257(7747) 29 May 1992, 38-42(5)
520 _aCheriton terminal for the Channel Tunnel is being designed as it is being built, thus creating enormous demands for the construction team and cost consultants. This article reports on the design, costing, planning and environmental impact of the terminal`s erection and the claims arising from it.
650 _aCHANNEL TUNNEL TERMINAL
650 _aCHERITON PASSENGER TERMINAL
650 _aDESIGN
650 _aTRANSMANCHE LINK
690 _aBUILDING AND CONSTRUCTION-PROJECTS