| 245 | _aPrefab refurb: mathematical tiles | ||
| 260 | _c1992 | ||
| 350 | _a0 | ||
| 490 |
_aArchitects` Journal _v195(21) May 1992, 43-46(4) |
||
| 520 | _aPeter Bell & Partners have devised a solution to the refurbishment of post- war prefabs, the aluminium shells of which are generally showing signs of deterioration. The proposed method is an overcladding of mathematical tiles. A cost analysis is included. | ||
| 650 | _aBUILT ENVIRONMENT-BUILDING COSTS | ||
| 650 | _aCLADDING | ||
| 650 | _aCOST ANALYSIS | ||
| 650 | _aMATHEMATICAL TILES | ||
| 650 | _aOVERCLADDING | ||
| 650 | _aPREFABRICATED HOUSES | ||
| 650 | _aTEMPORARY HOUSES | ||
| 690 |
_aRefurbishment _96264 |
||