000 01427cab a2200253 4500
001 ABS50819
008 090401t1994 xxu||||| |||| 00| 0 eng d
035 _a(Sirsi) u59303
041 _aeng
245 _aShanks & McEwan (Contractors) Ltd v Strathclyde RC
260 _c1994
350 _a0
490 _aConstruction Industry Law Letter
_v(1994) CILL 916-918(3)
520 _aCourt of Session. 11 February 1994. S were contractors for construction of a sewer for SRC. The contract was ICE 5th edition. SRC accepted tunnel segments which had cracked during the construction process provided they were made reasonably watertight. By letter SRC approved the tunnel segments as designed for incorporation in the works. S issued arbitration proceedings claiming additional costs incurred. The arbiter posed questions of law by way of case stated. Held that the arbiter was correct on both points. SRC assumed sole responsibility for the design of the segments thus absolving S from liability under the contract; the contract was varied entitling S to reimbursement for extra costs.
650 _aCIVIL ENGINEERING CONTRACTS
650 _aCLAIMS
650 _aDESIGN LIABILITY
650 _aICE CONDITIONS OF CONTRACT 5TH EDITION CL51
650 _aSHANKS AND MCEWAN(CONTRACTORS) LTD V STRATHCLYDE RC
650 _aVARIATIONS
690 _aBUILDING AND CONSTRUCTION-CASE LAW
942 _n0
948 _c04/03/1997
999 _c36377
_d36377