| 000 | 01621cab a2200241 4500 | ||
|---|---|---|---|
| 001 | ABS47206 | ||
| 008 | 090401t1992 xxu||||| |||| 00| 0 eng d | ||
| 035 | _a(Sirsi) u61047 | ||
| 041 | _aeng | ||
| 245 | _aImperial Chemical Industries v Bovis Construction and others | ||
| 260 | _c1992 | ||
| 350 | _a0 | ||
| 490 |
_aConstruction Industry Law Letter _v1992 CILL 776-778(3) |
||
| 520 | _aORC 17 February 1992. This action arose out of refurbishment and reconstruction of I`s corporate headquarters. I brought proceedings against the management contractor, the architects and the consulting engineers. The essence of the case was that by reason of breach of their obligations to I by each defendant, including the failure to co-ordinate and supervise works, the works took much longer and cost much more than they should have done. No attempt was made in the schedule of claims to link any particular defendant to any particular loss. A global claim was made for the sum of £19m plus professional fees. I accepted a plea from the defendants that the claim for delay and disruption was inadequately pleaded and I was ordered to serve new particulars. This was also unsatisfactory and I was ordered to serve a Scott Schedule containing inter alia the alleged complaint, the defendant against whom the complaint was made, which clause of the agreement had been breached and the alleged fact | ||
| 650 | _aCLAIMS | ||
| 650 | _aDELAYS | ||
| 650 | _aGOBAL CLAIMS | ||
| 650 | _aSCHEDULE OF CLAIMS | ||
| 650 | _aSCOTT SCHEDULES | ||
| 690 | _aBUILDING AND CONSTRUCTION-CASE LAW | ||
| 942 | _n0 | ||
| 948 | _c04/03/1997 | ||
| 999 |
_c37743 _d37743 |
||