100 _aCornes, D.
245 _aLate decision
260 _c1993
350 _a0
490 _aNew Builder
_v(164) 26 February 1993, 18(1)
520 _aCites "Balfour Beatty v Chestermount Properties" as example of where a contractor has passed the extended completion date, is causing delay, and is then instructed for a variation which has the effect of delaying completion further. In upholding the arbitrator`s decision in C`s favour, the court ruled that the developer`s architect had the right to grant extensions of time during a period of culpable delay by B, if employing the `net` basis of deductions rather than the `gross`.
650 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
650 _aCLAIMS
650 _aCOMPLETION DATE
650 _aCONTRACT CLAIMS
650 _aDEDUCTIONS
650 _aDELAY
650 _aEXTENSIONS OF TIME