245 _aTown and country planning costs
260 _c1995
350 _a0
490 _aEstates Gazette Case Summaries
_v(1995) EGCS 204(1) (7/1/95)
520 _a"R v SoS Environment and another, ex p Bexley LBC" QBD 13 December 1994. A disputed application for planning permission went to public inquiry, but the resulting settlement, in which the applicants foresook their costs, was not approved by B`s planning committee. When compromise was achieved the developer resumed its claim for costs, which was upheld by the inspector. On appeal, B was granted judicial review and the inspector was held to have acted unreasonably.
650 _aAWARD OF COSTS
650 _aCOSTS
650 _aDOE CIRCULAR 08/1993
650 _aPLANNING APPEALS
650 _aR V SOS ENVIRONMENT AND ANOTHER EX P BEXLEY LBC