_aBuilding _v260(7878) 3 February 1995, 41(1) |
||
| 520 | _aExamines the decision in "MJ Gleeson Group plc v Wyatt of Snetterton Ltd" CA 1994 clarifying the dispute resolution procedure in the FCEC subcontract form cl 18(2) which is widely used with the ICE Fifth Edition main contract in civil engineering. | ||
| 650 | _aCIVIL ENGINEERING CONTRACTS | ||
| 650 | _aDISPUTE RESOLUTION PROCEDURE | ||
| 650 | _aFCEC STANDARD FORM OF SUBCONTRACT CL18(2) | ||
| 690 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||