| 100 | _aPowell-Smith, V. | ||
| 245 | _aInterest: bad news but good law | ||
| 260 | _c1993 | ||
| 350 | _a0 | ||
| 490 |
_aContract Journal _v386(5927) 3 June 1993, 7(1) |
||
| 520 | _aComments on the clarification of ICE Conditions 6th ed Cl. 60(7) on the payment of interest, where an engineer has failed to certify an adequate amount. Refers to "SoS for Transport v Birse-Farr Joint Venture" (1993 unreported), a case heard under Cl. 60(7) of the 5th edition. | ||
| 650 | _aCERTIFICATES | ||
| 650 | _aCIVIL ENGINEERING CONTRACTS | ||
| 650 | _aCOMPOUND INTEREST | ||
| 650 | _aICE CONDITIONS OF CONTRACT 6TH EDITION CL60(7) | ||
| 650 | _aINTEREST | ||
| 650 | _aSCOTLAND | ||
| 690 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||