100 _aProctor, N.
245 _aContractors` escape route blocked up
260 _c1993
350 _a0
490 _aBuilding
_v258(22) 28 May 1993, 34-35(2)
520 _aSummarises "Balfour Beatty Building v Chestermount Properties" (1993), on the issue of calculation of liquidated damages for delay by the contractor, when a variation has been issued after the completion date. The court decision did not allow contractors to avoid liquidated damages in these circumstances.
650 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
650 _aCLAIMS
650 _aCOMPLETION
650 _aDELAY
650 _aEXTENSION OF TIME
650 _aJCT 1980 CL25.3.1
650 _aJCT 1980 CL25.3.5
650 _aLIQUIDATED DAMAGES
650 _aVARIATION
690 _aBUILDING AND CONSTRUCTION-CASE LAW