| 000 | 01253cab a2200217 4500 | ||
|---|---|---|---|
| 001 | ABS49126 | ||
| 008 | 090401t1993 xxu||||| |||| 00| 0 eng d | ||
| 035 | _a(Sirsi) u70123 | ||
| 041 | _aeng | ||
| 245 | _aBarclays Bank Plc v Fairclough Building Limited | ||
| 260 | _c1993 | ||
| 350 | _a0 | ||
| 490 |
_aConstruction Industry Law Letter _v1993 CILL 848-850(3) |
||
| 520 | _aChD 11 May 1993. The action involved two buildings of which the plaintiff (B) was the lessee. They had corrugated asbestos cement sheeting roofs. The defendant (F) carried out cleaning work on the sheeting which resulted in serious asbestos contamination. The buildings had to be taken out of use for a considerable length of time and a substantial clean-up operation was embarked upon. The contract between B and F was in the JCT Intermediate Form. It was held that F had failed to execute its works with reasonable care and skill and that they were in breach of the express terms of the contract by failing to comply with the asbestos regulations. | ||
| 650 | _aASBESTOS REGULATIONS | ||
| 650 | _aJCT INTERMEDIATE FORM | ||
| 650 | _aLAW REFORM (CONTRIBUTORY NEGLIGENCE) ACT 1945 | ||
| 690 | _aBUILDING AND CONSTRUCTION-CASE LAW | ||
| 942 | _n0 | ||
| 948 | _c04/03/1997 | ||
| 999 |
_c44114 _d44114 |
||