| 000 | 01499cab a2200277 4500 | ||
|---|---|---|---|
| 001 | ABS49129 | ||
| 008 | 090401t1993 xxu||||| |||| 00| 0 eng d | ||
| 035 | _a(Sirsi) u70135 | ||
| 041 | _aeng | ||
| 245 | _aTeam Service plc v Kier Management and Design Limited | ||
| 260 | _c1993 | ||
| 350 | _a0 | ||
| 490 |
_aConstruction Industry Law Letter _v1993 CILL 851-854(4) |
||
| 520 | _aCA 7 April 1993. The developers of a shopping centre employed the defendants (K) as a management contractor. The plaintiffs (T) were employed as subcontractors to design and build a car park. There was provision in the subcontract for T to recover interim payments which included a deduction of 3% for retention and a 2.5% cash discount. Twenty-three interim payments fell due of which only 10 were made within the required period, the others were late by up to 8 days. T claimed that by reason of this late payment they were entitled to interest by way of damages. They also claimed the 2.5% had been wrongly deducted. It was held that the 2.5% should be deducted as the above applied to all payments whenever made and the right to discount was not lost by late payment. | ||
| 650 | _aCAR PARK | ||
| 650 | _aCASH DISCOUNTS | ||
| 650 | _aINTERIM PAYMENTS | ||
| 650 | _aLATE PAYMENTS | ||
| 650 | _aMANAGEMENT CONTRACTORS | ||
| 650 | _aSHOPPING CENTRE | ||
| 650 | _aSUBCONTRACTORS | ||
| 650 | _aTHURROCK LAKESIDE | ||
| 690 | _aBUILDING AND CONSTRUCTION-CASE LAW | ||
| 942 | _n0 | ||
| 948 | _c04/03/1997 | ||
| 999 |
_c44123 _d44123 |
||