245 _aBlaenau Gwent BC v Lock
260 _c1994
350 _a0
490 _aConstruction Industry Law Letter
_v(1994) CILL 904-905(2)
520 _a19 January 1994. A series of payments for fluctuations was made to contractors under ICE conditions 5th edition Cl 60(6). After the 23rd payment the engineer accepted the contractors` revised calculations and the contractors increased their claims on the grounds that the earlier claims had been incorrect. The arbitrator subsequently agreed and awarded interest on the excess due to the contractors. This award was disputed by B on the grounds that the interest was not claimed when it became due. The decision in "SoS Transport v Birse-Farr Joint Venture" 1993 followed.
650 _aCIVIL ENGINERRING CONTRACTS
650 _aCLAIMS
650 _aICE CONDITIONS OF CONTRACT 5TH EDITION CL60(6)
650 _aINTEREST
690 _aBUILDING AND CONSTRUCTION-CASE LAW