| 245 | _aSetting a ceiling on costs | ||
| 260 | _c1997 | ||
| 350 | _a0 | ||
| 490 |
_aBuilding _v267(7981) 14 March 1997,39(1) |
||
| 520 | _aDiscusses how the Arbitration Act 1996 gives the arbitrator more power to cap recoverable costs in dispute proceedings unless both parties decide to intervene. | ||
| 650 | _aARBITRATION ACT 1996 | ||
| 650 | _aARBITRATORS | ||
| 650 | _aCOSTS | ||
| 650 |
_aDISPUTE RESOLUTION _96236 |
||
| 690 | _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ARBITRATION | ||