100 _aDodd, O.
245 _aConstraints on additional payments
260 _c1987
350 _a0
490 _aContract Journal
_v338(5625) 6 August 1987, 9(1)
520 _aThis article investigates whether claims for further payment including increased cost of labour and material would succeed under JCT 1980 , if clauses 4.6 and 4.5 were deleted from the Minor Works Form .
650 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS