| 245 | _aWhen is the job finished? | ||
| 260 | _c1997 | ||
| 350 | _a0 | ||
| 490 |
_aContract Journal _v389(6133) 9 July 1997, 17(1) |
||
| 520 | _aIllustrates how the almost universally accepted procedure for completion of building and civil engineering works differs from the actual forms of contract, causing problems for the courts in resolving disputes. | ||
| 650 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||
| 650 | _aCOMPLETION | ||
| 650 |
_aDISPUTE RESOLUTION _96236 |
||
| 650 | _aFORMS OF CONTRACT | ||
| 650 | _aINTERPRETATION | ||
| 650 | _aPRACTICAL COMPLETION | ||
| 650 | _aSUBSTANTIAL COMPLETION | ||