245 _aKelsey Housing Association Ltd v Ruddy Developments Ltd
260 _c1997
350 _a0
490 _aConstruction Industry Law Letter
_v(1997) CILL 1305-1307(3)
520 _aThere was a contract (JCT with Contractors Design 1981) between Kelsey as employers and Ruddy as contractors, for the construction of certain residential units. Disputes arose with Ruddy in particular claiming that kelsey had wrongfully refused to extend the completion date, and had wrongfully deducted damages for delay for which Ruddy were not responsible. The dispute arose prior to practical completion and was referred to arbitration.
650 _aKELSEY HOUSING ASSOCIATION V RUDDY DEVELOPMENTS
690 _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ARBITRATION