245 _aClaiming for off-site costs
260 _c1998
350 _a0
490 _aContract Journal
_v394(6179) 10 June 1998, 24(1)
520 _aReviews the case law relating to the payment of a contractor`s off-site overheads and profit in the event of a delay to a project.
650 _aALFRED MCALPINE V PROPERTY AND LAND CONTRACTORS
650 _aAMEC BUILDING LTD V CADMUS INVESTMENTS
650 _aBABCOCK ENERGY LTD V LODGE STURTEVANT LTD
650 _aCITY AXIS LTD V DANIEL P JACKSON
650 _aCONTRACTUAL CLAIMS
650 _aELLIS-DON V THE PARKING AUTHORITY OF TORONTO
650 _aHEAD OFFICE OVERHEADS
650 _aJ F FINNEGAN V SHEFFIELD CC
650 _aOFF-SITE OVERHEADS
650 _aST MODWEN DEVELOPMENTS V BOWMER AND KIRKLAND
650 _aTATE AND LYLE FOOD AND DISTRIBUTION LTD V GREATER LONDON COUNCIL
650 _aWHITTLE BUILDERS CO LTD V CHESTER LE-STREET DC