100 _aDelmon, J.
245 _aExpert determination and the allocation of costs
260 _c1988
350 _a0
490 _aInternational Construction Law Review
_v15(2) April 1988, 276-288(13)
520 _aDiscusses the use of an independent third party to provide interim dispute resolution in construction contracting. Considers the issue of allocation of costs of dispute presentation and, the costs situation where the binding decision of an independent third party is overturned. References.
650 _aALLOCATION OF COSTS
650 _aARBITRATORS
650 _aBABCOCK ENERGY LTD V LODGE STURTEVANT LTD
650 _aBINDING
650 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
650 _aCONSTRUCTION DISPUTES
650 _aBUILDING CONTRACTORS
650 _aCOSTS
650 _aEMPLOYERS
650 _aENGINEERS
650 _aFIDIC
650 _aINDEPENDENT THIRD PARTIES
650 _aINTERIM DISPUTE RESOLUTION
650 _aINTERNATIONAL CHAMBER OF COMMERCE
650 _aTATE AND LYLE FOOD AND DISTRIBUTION LTD V GREATER LONDON COUNCIL
690 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS