| 520 | _aQBD 18 March 1998. Operational development - dwelling and garage - building across line of footpath - garage completed and then part demolished before inquiry - whether developmenbt substantially completed - implementation of planning permission - whether spent - confirmation quashed. Taken from report header. | ||