| 245 | _aFinal certificate issue - keeping to a strict timetable | ||
| 260 | _c1987 | ||
| 350 | _a0 | ||
| 490 |
_aContract Journal _v339(5633) 1 October 1987, 7(1) |
||
| 520 | _aDiscusses the amendments to JCT 1980 clause 30 governing the issuing of the final account and final certificate in a building contract. Mentions the decision in Fairclough Building Ltd v Rhuddlan Borough Council , CA 24 July 1985, see Abstract 35560. | ||