| 520 | _aOutlines the roles played by client, planning supervisor, designer, principal contractor and main contractor in applying the Construction Design and Management Regulations 1995 through the five stages of a construction project from feasibility to handing over to the client. Summarises the main objectives of the Project Health and Safety Plan, Project Health and Safety File, Pre-tender Health and Safety Plan and the Construction Phase and Health and Safety Plan. | ||
| 650 | _aCONSTRUCTION (DESIGN AND MANAGEMENT) REGULATIONS 1994 | ||
| 650 | _aCONSTRUCTION (DESIGN AND MANAGEMENT) REGULATIONS 1994 | ||
| 650 |
_aHEALTH AND SAFETY _96244 |
||
| 650 | _aLIABILITY | ||
| 650 | _aPLANNING SUPERVISORS | ||
| 650 | _aSITE SAFETY | ||
| 690 | _aBUILT ENVIRONMENT-BUILDING STANDARDS | ||