100 _aKnowles, R.
245 _aNo obligation
260 _c1987
350 _a0
490 _aChartered Quantity Surveyor
_v10(2) October 1987, 7(1)
520 _aReviews the decision in Glenlion Construction v The Guiness Trust , ORC 28 July 1987, see Abstract 38052, in which a dispute arose out of an early completion programme in a building contract. It was held that the architect was under no obligation to comply with the programme. Also briefly comments on Temloc v Errill Properties , CA 29 July 1987, see WB2334-10, which considered the provisions of JCT 1980 cl. 24.2.1 concerning damages for late completion .
650 _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ARBITRATION
650 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
650 _aCOMPLETION DATE
650 _aJCT 1963
650 _aLIQUIDATED DAMAGES