_aBuilding _v(41) 15 October 1999, 65(1) |
||
| 520 | _aIn "Macob Civil Engineering v Morrison Construction Ltd" the decision showed that an adjudicatorαs ruling was enforceable, even if there had been a procedural error. Discusses a new case, "Project Consultancy Group v Trustees of the Gray Trust'" that shows the court drew a distinction between a decision that was invalid because of alleged procedural error, and a decision that was not within the jurisdiction of the adjudicator to make under the relevant act. | ||
| 590 | _aABS | ||
| 650 | _aMACOB CIVIL ENGINEERING LTD V MORRISON CONSTRUCTION LTD | ||
| 650 | _aPROJECT CONSULTANCY GROUP V TRUSTEES OF THE GRAY TRUST | ||
| 650 | _aPROCEDURE | ||
| 650 | _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION | ||
| 650 | _aDISPUTES | ||