| 245 | _aHarbour & General Works Ltd v Environment Agency | ||
| 260 | _c1999 | ||
| 490 |
_aConstruction Industry Law Letter _v [1999] CILL 1556-1559 |
||
| 520 | _aCA 12 October 1999. Extension of time in which to commence arbitration under Arbitration Act 1996 s12. 'Final & binding' under ICE conditions of contract, clause 66. ICE Arbitration procedure, rule 5.2. (Taken from journal headnote) | ||
| 650 | _aHARBOUR AND GENERAL WORKS LTD V ENVIRONMENT AGENCY | ||
| 650 | _aARBITRATION ACT 1996 S12 | ||
| 650 | _aICE CONDITIONS OF CONTRACT 5TH EDITION CL66 | ||
| 650 | _aICE ARBITRATION PROCEDURE | ||
| 650 | _aTIME LIMITS | ||
| 690 | _aARBITRATION-CASE LAW | ||